Good News, Recognitions & Announcements

Girls Track and Field State Champions

Members of the Festus High School Girls Track and Field Team, along with their Coaches, were recognized by the Board of Education for capturing the 2026 Class State Championship. This marks the second consecutive year the Lady Tigers have earned the state title, an outstanding achievement that reflects the dedication, talent, and hard work of our student-athletes and coaching staff.
The Boys Track and Field Team was also recognized for its fourth-place finish at the state meet. This accomplishment is especially significant as it marks the first time in Festus High School history that both the boys and girls track and field teams brought home state trophies from the same championship meet.
A group of young women in pink t-shirts stand in a meeting room, facing a table with people seated.
 

Consent Agenda

Approved unanimously. Items were:

  • May regular session minutes
  • Bills payable for June
  • May Financial Report
  • June Ledger Subtotals
  • 2026 Distinguished Service Award recipient
  • 2026 Hall of Fame inductee
  • Card Access System Service Agreement
  • MOU with City of Festus for the SRO Program
  • AMI DESE application
  • Updated Job Description Handbook
  • High School Handbook updates
  • Budget amendment to match year end expenditures and revenues for FY '26
Regarding the FY2026 budget, the District concluded the fiscal year by receiving 101% of anticipated revenues. This slight increase was primarily driven by higher-than-expected local revenues, which helped offset a reduction in state funding.
Year-end expenditures aligned with projections, totaling 100% of budgeted costs.
As a result of the modest revenue increase and the District's intentional pause in discretionary spending within Fund 1 to prepare for anticipated revenue reductions in the next two years, the District ended the fiscal year with a healthy operating reserve of 36%.

 

Communication and/or Reports

Superintendent's Report

  • There will be a Classified Job Fair on Wednesday, August 5 from 9am - Noon in the lobby of the Performing Arts Center.
  • Summer school enrollment was up about 77 students this year over last year. We are ending summer school with 1237 students.

CSIP Approval

The Board of Education unanimously approved the District's new 2026–2031 Continuous School Improvement Plan (CSIP), The Festus Five: Building Our Future Together. Developed through a collaborative process that included input from staff, students, parents, community members, and the Board of Education, this five-year strategic plan will serve as the District's roadmap for continuous improvement. The plan establishes five strategic priorities that will guide decision-making, resource allocation, and district initiatives while ensuring a continued focus on student success, organizational excellence, and preparing every learner for the future: The Festus Five.
 

Prior & New Business

Facilities Report and Recommendations

Brockmiller Construction provided an update on the District's ongoing construction projects.
Intermediate School
  • The interior addition is nearing completion, with only minor finish work remaining.
  • Exterior work continues, with concrete complete on the east side and work beginning on the west side to complete the playground surface. Playground equipment installation is scheduled to begin the week of June 29.
Middle School
  • The project is complete; however, landscaping did not establish as expected. Sod will be installed near the main entrance and band room entrance, with slit seeding planned for the remaining areas.
High School Gym/Fieldhouse
  • Site grading for the indoor fieldhouse is nearly complete. Topsoil placement is scheduled for the week of June 29, followed by sod installation.
  • Approximately 22,000 cubic yards of fill have been placed to date, with additional fill still needed.
  • The utility berm has been completed.
  • Approximately 2,000 linear feet of storm pipe has been installed, with about 1,000 linear feet remaining.
  • Waterline relocation is scheduled for the week of June 29.
  • Electrical conduit installation through the high school is underway to connect the new facility.
  • Bid Package #4, which includes the remaining fieldhouse construction work, has been released. Bids are due July 7.

Pounds Road House Demolition

The District solicited bids from 19 contractors for the demolition of two homes located on Pounds Road adjacent to the Transportation Department. The Board of Education approved the low bid of $62,346 from Saline Creek Grading to demolish the two homes and a detached garage. As part of the project, the concrete foundations will be recycled and used as fill material. Once the site is cleared, the area will serve as temporary parking for bus drivers.

2026-2027 Perpetual Calendar

The Board of Education approved the 2026–2027 Perpetual Calendar, which serves as the annual schedule of recurring agenda items to be presented throughout the school year. In addition to these regularly scheduled reports and action items, the Board will continue to consider other business and timely matters as needed.

2026-2027 Board of Education Meeting Dates

The Board of Education approved the dates of their meetings for the 2026-2027 school year.

Curriculum Development Cycle 2026-2027

The Board of Education approved the 2026-2027 K-12 ELA Standards and the K-12 World Languages Standards.

Fiscal Year '27 Budget

The Board of Education approved the District's FY2027 operating budget, as required by Missouri law prior to June 30. Because the Governor had not yet signed the state budget at the time of approval, significant uncertainty remains regarding state funding. The District adopted a conservative "worst-case scenario" budget based on an estimated state adequacy target (SAT) of approximately $6,800 per student in anticipation of potential state revenue shortfalls.
Projected Revenues
  • Fund 1: $19.4 million
  • Fund 2: $23.8 million
  • Fund 4: $4.8 million
Projected Expenditures
  • Fund 1: $17.5 million
  • Fund 2: $25.9 million
  • Fund 4: $6.5 million
The proposed budget includes a planned deficit of approximately $150,000 in the District's operating funds (Funds 1 and 2) and projects an ending operating reserve of approximately 27%.